Road Design Exam Guide
Exam-day guide

Highway geometric design,
made visual.

Everything from the four recorded classes — the ERA Geometric Design Manual concepts, the Civil 3D practice and the InRoads retaining-wall project — rebuilt as short notes, moving diagrams you can play with, and a practice quiz.

1 · Read in orderEach section has a one-line summary, the key notes, and an interactive figure. Drag the sliders.
2 · Watch the ★ boxesYellow boxes mark what the lecturer repeated most. Those are the likeliest exam questions.
3 · Take the quizPick a topic or do all of it. Every answer explains why, with a link back to the section.

Numbers to know cold

Tap any card to jump to its section.

Part A — Design concepts (ERA Geometric Design Manual)
01

How a road project happens

Lecture 1 · 01:04 – 05:35

Study → consultant designs (survey + ERA standards) → contractor builds → as-built survey checks what was built.

  • Every road job has two sides: the consultant (design and supervision) and the contractor (construction).
  • A road starts with a study of whether it pays: transport needs, goods movement, economic benefit. Example from class: the old two-lane Addis Ababa–Debre Zeit road could not carry growing traffic, so a new road was needed.
  • ERA tenders the design to consultants. Design can take 5–6 years before the job is awarded to a contractor.
  • Survey first: GPS control points are monumented in concrete and protected; then benchmarks (BM1, BM2 …) are set, and ground points and cross-section points are picked along the route.
  • The designer’s goal: minimum excavation and earthwork — that is what saves the government budget, especially in mountainous northern Ethiopia.
The life of a road projectclick the steps
Click a number or use Next. Step 6 comes back in Part B: the as-built survey plus the original ground gives the real earthwork quantity.
02

Three views of one road: plan, profile, cross-section

Lecture 1 · 02:36 – 05:35

Horizontal alignment = WHERE (location). Vertical alignment = HOW HIGH (elevation). Cross-section = WHAT is built at each station, every 20 m.

Lecturer repeated this“The road is cut every 20 m and a design comes out for it.” For a 10 km road, sections must come out every 20 m for the whole 10 km. The cross-section shows the asphalt, base and sub-base, and where earthwork (cut or fill) is needed.
  • Horizontal alignment (plan view): the route on the map. It tells you the location (easting, northing).
  • Vertical alignment (profile): the road’s elevation along its length. It tells you the elevation at every point.
  • Cross-section: a slice across the road at a station. It shows the pavement layers and the earthwork.
  • A station (chainage) is written km + metres: 0+120 means 120 m from the start.
One station, three viewsdrag the station · press drive
The red line on the plan is where the road is “sliced”. Where the blue grade line is below the ground you cut (back slopes go up). Where it is above, you fill (side slopes go down).
03

Traffic (AADT) decides the design class

Lecture 1 · 05:36 – 10:04

AADT = Annual Average Daily Traffic. It puts the road in a design class (DC1 … DC8), and the ERA manual then gives the standards for that class.

  • How it is counted: a person stands at the road with a form and ticks every vehicle that passes (small car, big truck …).
  • What AADT decides: the pavement thickness (together with axle load), the number of lanes (2 or 4), whether the road is paved (asphalt) or gravel, and the design speed.
  • Design speed also depends on terrain: flat, rolling, mountainous, escarpment (and urban).
  • Axle load is calculated and used to decide the thickness of the road layers.
  • A new road with no traffic yet? The government or the Ministry of Transport decides it, e.g. because many goods will move on it and it pays off economically.
  • Money back: an expressway repays itself through tolls and can cover its own maintenance. A fuel levy — about 10% when fuel is imported — goes to the Road Fund for maintenance.
Count the traffic → find the classdrag the slider
The lecturer’s two examples are 150–300 vehicles/day (a low class) and 10,000–15,000 → DC8, a dual carriageway of 2 × 7.3 m. The other bands and speeds are taken from the ERA 2013 manual tables — check your copy if the exam asks for exact figures.
04

Parts of the road cross-section

Lecture 1 · 10:05 – 15:28

Carriageway, shoulder, median, side drain, back slope (cut, goes UP), side slope (fill, goes DOWN) and berm.

Anatomy of a dual carriagewaytap a part or a chip
Switch between FILL and CUT. In cut the back slope climbs from the ditch to the original ground. In fill the side slope runs down to it.

Shoulder — why it shrinks in the mountains

  • Purposes: room for pedestrians, protection from water (its main benefit is a longer road life), and road users’ comfort.
  • ERA standard for DC8: 3 m on flat, 3 m on rolling, only 0.5–2.5 m in mountainous terrain.
  • Why: in mountains there are back slopes and side slopes on both sides. The wider you make the shoulder, the more you must dig, and the budget rises fast. So shoulders are reduced in mountainous and escarpment terrain.
Lecturer repeated thisMountain terrain → reduce widths → less excavation → less cost. The same idea runs through the whole course: earthwork drives cost.
Wider shoulder = much more diggingdrag the shoulder width
On a hillside, widening each shoulder from 0.5 m to 3 m roughly doubles the rock and soil that must be dug out, for every metre of road.

Median — think about the future

  • Outside towns, medians are made wide (10–15 m). Compensation is paid once for the land (right of way). When traffic grows, a lane is added inside the median without new compensation.
  • Right of way is a big problem on road jobs: cemeteries, churches and other places that cannot be touched force the road to change direction.
  • In the city, sidewalks are now about 6–7 m (because of the corridor project), for pedestrians and green area.
05

Water is the road’s #1 enemy

Lecture 1 · 15:29 – 18:48 and 41:28 – 45:25

Get rain off the road fast (crown → ditch). Wet expansive soil swells and shrinks → potholes. Compact at the Optimum Moisture Content (OMC) to 95–99% of lab density.

Lecturer repeated this“The main purpose of the road [drainage] is to avoid water.” The shoulder’s main job is to increase road life. Water must run quickly into the side drain.
Rain on a crowned road vs a flat roadanimated · switch the mode
The 2.5% crown sends water to the ditches. With no cross-fall, water ponds, soaks into the base, and expansive clay swells and shrinks until a pothole forms.

Expansive soil

Expansive (black-cotton type) clay expands when it gets water and shrinks when it dries. That repeated movement under traffic creates potholes. The fix is drainage: make the water run quickly into the side drain.

Compaction and OMC

  • Asphalt roads have a base course and a sub-base. Each layer is compacted at the Optimum Moisture Content (OMC).
  • The lecturer’s analogy: it’s like beso (roasted-barley flour) — it only holds together with the right amount of water.
  • Target: 95% – 99% of the laboratory (maximum) density.
  • If water gets in later, the layer soaks, shrinks when it dries, and sinks under load. Materials engineers use Atterberg limits and the traffic to decide the pavement thickness.
Compaction curve: why “optimum” moisturedrag the water content
Too dry, the grains don’t slide together. Too wet, water takes up the space. Maximum density comes at the OMC, and the spec is 95–99% of it.

Water on slopes and landslides

  • Water density is 1,000 kg/m³. Soil that soaks up water gets heavier, and with load on top it starts to slide (e.g. the landslide that cut the road near Shashemene).
  • So a cut-off (“furrow”) ditch is dug on the hill above the cut, to turn the water back before it reaches the slope.
Student question: are earthquakes and weather (rain, snow) in the standard? Answer: yes, but in the pavement materials and thickness, not the geometric design. In very rainy places like Gambela, work happens only about 6 months a year — you can’t reach density in the rain because the material is past its OMC. Seismic design uses zones (active volcano, rift valley). A dangerous area can be treated as an obstruction and the route moved.
06

Gradients & types of curves

Lecture 1 · 18:49 – 22:30

Avoid closely spaced contours. Max gradient in towns is 8% (sometimes 6%). Trucks can’t climb more than about 12%, so steep hills need switchbacks.

  • Closely spaced contours = steep ground. Try to avoid them when choosing the alignment.
  • If there is a big hill over a short distance: max gradient in town 8%, sometimes 6%.
  • Otherwise use switchback curves (S-curves), like the road up Entoto. The lecturer’s example: to climb 1 m you travel 20 m (5%), because vehicles can’t climb more than about 12% safely.
How steep is too steep?drag the gradient
Gradient % = vertical rise ÷ horizontal distance × 100. True scale, so 12% really does look this steep.

Curve types (know all four)

Normal, compound, reverse, broken-backdiagram
Simple / normal R one arc, one radius Compound same direction, 2 radii Reverse (S) opposite directions, back-to-back Broken-back same direction + shorttangent between (avoid)
Broken-back curves (two curves turning the same way with a short straight between) look and drive badly. Designers replace them with one longer curve or a compound curve.
07

Sight distance (SSD & PSD)

Lecture 1 · 22:31 – 26:15 · ERA manual Chapter 7

SSD = distance to see a hazard, react and stop. PSD = distance needed to overtake safely. Both are limited in the ERA manual according to design speed and friction.

  • Stopping Sight Distance (SSD): the distance a driver needs to stop, counting the reaction time.
  • Passing Sight Distance (PSD): the distance needed to overtake safely (much longer than SSD).
  • Both depend on design speed and the coefficient of friction between tyre and road. Friction differs for asphalt vs gravel.
  • Both are found in Chapter 7 of the ERA manual.
SSD = reaction distance + braking distancechange speed · run the brake test
Standard formula: SSD = 0.278·V·t + V² / (254·f), with V in km/h, t in s and f the friction coefficient. The friction values here are illustrative; use the manual’s table values in calculations.

Crest and sag vertical curves

  • Crest (hill top): the curve must be long enough that a driver can see a car coming over the hill in time.
  • Sag (valley): at night, headlight light hits the road ahead. The curve is designed with headlight sight distance, so the beam lights enough road and isn’t reflected back into the eyes.
What limits sight on vertical curvesanimated · switch crest / sag
Crest: the hill itself blocks the line of sight (red = blocked, green = clear). Sag: the rising road ahead “catches” the headlight beam early.
08

Curves: radius, widening, transition & superelevation

Lecture 1 · 26:16 – 36:00 · 133:06 Q&A

Bigger radius = flatter (closer to a straight line); smaller radius = sharper. Sharp curves need widening and superelevation (tilt) against centrifugal force.

Student Q&A“When the radius gets smaller the curve gets sharp. When you increase it, it gets flat and approaches a straight line.” That is how you fix the Civil 3D warning: increase the radius.

Curve widening

  • On a tight curve, a long vehicle leaves its lane and enters the other lane, so the road is widened on curves.
  • R > 250 m → no widening needed. R 120–150 m → widen 0.6 m.
  • Fill widening: where the fill is higher than 3 m, widen about 30 cm to the side, for psychological reasons — drivers fear the drop.

Transition (spiral) curve

A transition curve (spiral) between the straight (tangent) and the circular curve lets the car enter the bend gradually, not with a sudden turn of the steering wheel.

Radius vs speed — when is a curve too tight?drag radius and speed
Minimum radius comes from e + f = V² / (127·R). At 50 km/h with e = 8% the ERA manual gives about 80 m. That is why the lecturer’s 50 m radius in Civil 3D showed a warning, and 80–100 m fixed it. The yellow band is the extra width on the inside of the curve (exaggerated).

Superelevation

  • Entering a curve, centrifugal force pushes the vehicle outward. Superelevation tilts the road (outer edge raised) to balance it.
  • Normal crown slope = 2.5% (both sides falling away from the centre) — for drainage.
  • Maximum superelevation = 8% (rural, in Ethiopia) and 4% in towns.
  • The length over which the outer edge goes from −2.5% to +8% is the run-off length (L).
Watch the road tilt into the curveanimated · or drag the position
Tangent: normal crown. The outer edge then rises: first the adverse crown is removed (0%), then the section becomes a plane, then it rotates to full superelevation in the circular curve. Rotation is about the centre line.
09

Earthwork — the biggest cost on a road

Lecture 1 · 36:01 – 41:27

The main cost of road building is earthwork, not pavement. Balancing cut and fill is the designer’s biggest job.

Lecturer repeated this“In road work the main cost is not the pavement — it is the earthwork.” And: “Balancing earthwork is the designer’s biggest job.”
  • Even 8% superelevation, which looks small, makes the side slope much longer on a high fill. That increases both fill and cut quantities.
  • Fill is placed and compacted in 20 cm layers, each tested. So 3 m of fill = 15 tests.
  • Quantities come from cross-sections (every 20 m). End-area method: V = (A₁ + A₂) / 2 × distance.
Building an embankment layer by layerdrag the fill height
Each 20 cm layer is spread, rolled and density-tested before the next one goes on. Vertical scale exaggerated.
Balance the cut and fillmove the grade line
Volumes use the end-area method between sections every 20 m (10 m road, 1:1.5 slopes). A balanced design reuses its own cut as fill, with no borrow pit and no spoil dump.
10

Retaining walls, benches & weep holes

Lecture 1 · 45:26 – 55:56 (student questions)

Use a retaining wall when a slope would run too far or space is tight. Masonry up to 8–10 m, concrete above. Weep holes are a MUST.

  • When: e.g. in the Abay gorge one side drops away. A normal 3:1 fill slope would never reach the ground, so a retaining wall is chosen.
  • Masonry (stone) walls up to about 8–10 m. Higher → concrete shear wall.
  • In the city there is no space for side slopes, so retaining walls save space (and look good).
  • Cut bench: in high cuts in a mountain, a bench with a berm is made about every 10 m.
  • Fill on sloping ground: new soil won’t bond to sloping ground, and vehicles add a surcharge load that pushes it off. So steps (benches) are dug about every 3 m, and the roller compacts step by step.
Weep holes are mandatory. If water can’t get out through weep holes it builds hydrostatic pressure and overturns the wall. Walls near the Abay bridge built in the 1990s failed because they held water.
Rain behind a retaining wallanimated · toggle weep holes
Water pressure grows with depth (blue arrows) — p = ρ·g·h with water at 1,000 kg/m³. Weep holes let it out, so the pressure never builds up.
11

Flexible vs rigid pavement

Lecture 1 · 55:57 – 58:49

Flexible = asphalt (layers, flexes, expands/shrinks). Rigid = concrete slab (heavy loads, but joints every ~5 m make the ride bumpy).

Flexible (asphalt)

  • Layered: asphalt → base → sub-base → subgrade
  • Never reaches 100% density
  • Expands and shrinks
  • Smooth riding comfort

Rigid (concrete)

  • Concrete slab spreads load widely
  • For heavy loads: factories (e.g. near cement plants), sandy areas like Metehara
  • Drawback: expansion joints about every 5 m → vehicle jolts → poor riding comfort
How each pavement carries a wheel loadanimated · switch type
The red zone is how the wheel pressure spreads into the ground. The strip below shows the ride: smooth on asphalt, bump-bump on concrete joints.
12

Drainage design & material tests

Lecture 1 · 58:50 – 73:17

The hydrologist uses Q = C·I·A and Manning’s formula, then decides culvert, bridge or ford. The materials engineer samples every 500 m (CBR, Atterberg limits, PI).

Hydrology

  • Rational formula Q = C · I · A — C = runoff coefficient (surface type), I = rainfall intensity, A = catchment area.
  • Manning’s formula is then used to set the ditch width and depth.
  • The hydrologist decides whether a culvert, bridge or ford is needed.
Runoff from a catchmentchange surface, rain, area
Paved surfaces shed almost all rain (high C). Forests soak much of it up (low C). C values shown are typical textbook numbers.

Materials

  • The materials engineer takes a sample about every 500 m and tests CBR (California Bearing Ratio), Atterberg limits and the Plasticity Index.
  • If the soil is weak, capping material is added, or about 1 m is excavated and replaced.
Student question: on a 40 km road the soil can change between samples — why not every 100 m? Answer: CBR and Atterberg tests are expensive, so cost goes up a lot. The General Specification says 500 m. A short road (e.g. 1 km) may use 100 m, but only if it is written in the Special Conditions of Contract.
13

Utilities in city roads

Lecture 1 · 73:18 – 77:00 (student question)

Power, telecom and ICT go under the sidewalk/shoulder. The sewer is the exception: deep (3–4 m) and under the carriageway.

What’s under the streettap a utility
Cables and ducts would break under the carriageway because of heavy loads. A sewer needs a continuous grade, so it goes deep — which is why manhole covers sit on the asphalt.
Part B — Software practice (Civil 3D & InRoads)
14

Civil 3D: survey points → surface → alignment

Lecture 1 · 77:01 – 147:10 (Adama–Wonji survey data)

Clean the data in Excel → import the points → create the surface (max triangle length 70) → contours → polyline from CL points → alignment → apply the ERA design criteria → fix the warnings by increasing the radius.

  1. Excel: fix the survey data. Each point has Northing, Easting, Elevation, Description.
  2. Import points into Civil 3D and create a surface. Set maximum triangle length = 70 m.
  3. Contours: if they are too crowded, edit the style: 0.25 m minor, 1.25 m major.
  4. Centreline: filter only the CL points. In Excel: =CONCATENATE(Easting, ",", Northing) → copy → in Civil 3D type PL (polyline) and paste.
  5. The surveyor’s CL may come out zigzag. The designer looks at the contours and chooses the better path.
  6. Alignment → Create Alignment from Objects → pick the polyline → name it “CL”.
  7. Design Criteria tab → tick Use criteria-based design → design speed 50 km/h → load the ERA design criteria file (XML) → e max 8%, 2-lane → OK.
  8. Yellow warning symbols appear = a curve is outside the design standard: the radius is too small, or the tangents overlap.
  9. Fix: Alignment → Alignment Creation Tools → Alignment Grid View → increase the radius (e.g. 50 → 80 or 100) → the warning disappears.
Excel → AutoCAD polylineedit the numbers
CONCATENATE glues X and Y with a comma, “E,N”. That is exactly what AutoCAD’s PLINE accepts when you paste. (Add a third “,Z” for 3D points.)
Why Civil 3D shows the yellow ⚠change the radii and speed
Two kinds of violation: a radius below the minimum for the design speed, or tangents overlapping (T₁ + T₂ longer than the distance between the PIs). Start at 50 m like the lecturer, then raise it to 80–100 m.
End of class 1: the surveyor gives the OG (original ground). After construction an as-built (or rock-topo) survey is taken. Cross-sections combine the OG, as-built and design surfaces → the exact earthwork quantity → the contractor’s payment is checked. Next class: profile and cross-section. (Student asked about AI: yes — modern AI tools can write scripts that once took LISP programming.)
15

Check the survey data, then build the TIN

Sessions 2 & 3 · voice recording

Never triangulate raw data. Remove wrong codes (e.g. “RB”), save clean CSV, triangulate with a sensible max length (class: 70), and press Apply.

Lecturer repeated this (≈6 times)“Whenever any data comes, we must check each one.” Wrong data gives false figures to the client — the contractor is either harmed or gets paid unfairly.
  • The RB problem: the as-built file mixed wall-top points (≈2386 m) with points coded RB at a different level (wall bottom). Triangulated together, the triangles link the two levels and give in-between, wrong elevations. So filter RB out and keep it separately.
  • A survey file must always come with a legend that explains its codes. Without one, you work out the codes from the values.
  • An Excel filter only HIDES rows — they are still data. Delete them, or copy the clean rows to a new file.
  • Save as CSV (comma delimited). A CSV keeps only the active sheet; an .xlsx workbook keeps all sheets.
  • Maximum triangle length depends on the point spacing. Dense data: 10–30 (e.g. points every 5 m → about 20–30 for OGL, 15–20 for RL). The class used 70 for all four surfaces.
  • Triangulate after all imports, and press Apply — nothing happens until you do. The triangle count that appears confirms it worked.
Triangulation: max length and bad codesdrag the length · toggle RB
Too long a limit lets false triangles bridge areas with no data. Too short leaves holes. Leaving the RB points in drags triangles down to the wall-bottom level (red).
16

InRoads basics: platform, file types, saving

Session 2 · voice recording

InRoads (Bentley) runs on MicroStation and saves every item as its own file. Open the .xin first; save separately, then bundle them in a .rwk project.

Platforms

  • Civil 3D runs on AutoCAD (so did Eagle Point).
  • InRoads runs on MicroStation; in class MicroStation is only used to delete and zoom.
  • InRoads can open DWG but lags (e.g. with contours); DGN works best.
  • MicroStation level = AutoCAD layer.

Preparing the drawing

  • Save the DWG as AutoCAD 2004 format so InRoads can read it ★
  • Take just the line you need: Copy with Base Point → new drawing → Paste to Original Coordinates (real coordinates kept)
  • Trim (TR) / delete the rest
  • Keep work on the D: drive, not C: or the Desktop
ExtensionWhat it holdsRemember
.xinPreferences: styles, colours, labels (“civil.xin”)Open it FIRST, or you get default colours and labels ★
.dtmOne surface (OGL.dtm, As-built.dtm …)Keep in a “Surfaces” folder
.algGeometry project: horizontal and vertical alignmentsOne project can hold many alignments
.itlTemplate library (typical sections)Saved separately from the roadway file
.irdRoadway Designer (corridors)Combines alignments + templates
.rwkProject file — opens everything at onceSave As → Project → tick the items → “Add and Update”
.csvSurvey points, comma-delimitedRead with the Text Import Wizard
Why separate files? If one file breaks, the others are safe, and you can fix one alignment out of 6–7 without touching the rest. The .rwk project is just the convenient “open everything” layer. File → Save on a template saves only the template.
17

InRoads: surfaces and alignments

Session 2 · session 3 · voice recording

Make 4 surfaces → import CSV with the Text Import Wizard → triangulate → set symbology → horizontal alignment from graphics → two vertical alignments from surfaces (VL Top, VL Bottom).

The four surfaces ★

SurfaceMeaningUsed for
OGL (existing)Original ground level — natural ground before worksThe active surface; excavation is measured from it
As-builtSurvey of what was actually built (wall top)Gives VL Top
Rock topTop of the rock layerCalculation (rock vs soil)
RL (Reduced Level)Bottom / founding level (lean concrete)Gives VL Bottom
  1. File → Open → civil.xin (if it isn’t listed, change “files of type” to Preferences / All Files).
  2. File → New → Surface — create OGL, As-built, Rock top, RL (just the names, Apply each).
  3. File → Text Import Wizard — import type must be Surface (the same wizard also imports alignments!). Browse with “…”, choose the start row (skip headers), comma delimited. Every column says Skip: right-click to set Northing, Easting, Elevation (description optional). On the last page pick the target surface and a Seed Name. A report shows the point count and min/max elevation.
  4. Surface → Triangulate Surface — max length 70 → Apply. Check the triangle count.
  5. Symbology (Surface Properties → More → Advanced): OGL → Existing Ground, As-built → As-built, Rock top → Rock top, RL → Reduced Level (red). Apply for each surface. Each surface then shows in its own colour on profiles and cross-sections.
  6. File → Import → Geometry → From Graphics — type = Horizontal Alignment, name it (e.g. “Center” / “Masonry”) → Apply → pick the line at the end where 0+000 should be → accept (right-click). Check with Geometry → Review Horizontal.
  7. File → Import → Geometry → Vertical from Surface (with the horizontal alignment selected): As-built → VL Top; RL → VL Bottom. “Successful completion” appears. View with Evaluation → Profile → Create Profile.
  8. Save each surface (.dtm), the geometry (.alg), then the project (.rwk).
Horizontal BEFORE vertical — alwaysA vertical alignment is entered as station + elevation. Stations only exist along a horizontal alignment, so a vertical alignment cannot be created first. (The lecturer’s own “Vertical from Surface” failed live because no horizontal alignment was selected.)

Minimum data for a horizontal alignment

Start point + each PI’s Easting and Northing + Radius (plus spiral-in / spiral-out if there are transition curves). The software does not need PC or PT — it calculates them.

Minimum data for a vertical alignment

Station, PVI elevation, and vertical curve length (“three things minimum”). More is optional.

Why two vertical alignments? With only one, the template would give a fixed wall height (3.40 m everywhere). VL Top (as-built) plus VL Bottom (RL) let the real height change at every station, so the quantities are real.
Which side is “left”? It depends where you clickedswitch the pick direction
Left and right are judged looking toward increasing stations. Students who picked the line from opposite ends got 0+000 at opposite ends, with left and right swapped — and different results.
Geometry from graphics has no curves: every vertex of a drawn polyline becomes a PI, which is why stations looked cluttered. Importing the same line twice creates overlapping alignments (Center1, Center2 …).
18

Templates: components, constraints, origin, end conditions

Session 3 · voice recording (retaining-wall project)

Components are closed shapes of KNOWN size (wall, concrete). End conditions SEARCH for a surface (earthwork). Constrain every point except the two that ride the alignments.

The retaining-wall template riding two alignmentsmove the station · tap parts
The origin (top) follows VL Top. The bottom point is pulled to VL Bottom by a Point Control. So the masonry height changes with the real data, and the end conditions climb until they hit the OGL.

Building it (Modeler → Create Template)

  1. Template library: right-click → New → Folder (e.g. “Training”/“Class”) → right-click → New → Template. Start fresh for each project.
  2. Right-click → Add New Component → Constrained. Click the points, right-click → Finish (Close Shape). The click order doesn’t matter, but the first point has no constraint, so put it at the bottom.
  3. Name and style FIRST — double-click the component: Name + Style (Lean Concrete, Cyclopean, Retaining Wall), with Closed Shape ticked.
  4. Double-click each point → set Horizontal and Vertical constraints to a parent point (negative = left or down). A Slope constraint keeps the battered face — the software computes the %.
  5. Set the two control points (top and bottom) to None / None so the alignments can drive them.
  6. Right-click → Change Template Origin → click the top point (→ Set Dynamic Origin). For a new road the origin is at 0,0 on the centre line.
  7. Right-click → Add New Component → End Condition, name and style “Cut”: segment 1 = 0.5 m horizontal, Check for Interception OFF; segment 2 = vertical, interception ON, End Condition is Infinite ✓. Mirror for the other side (−0.5).
  8. Test → Draw a trial ground (e.g. a 10% slope) to see the end conditions work. Save the template library.
ItemValue used in class
Lean concrete (blinding)2.60 m wide × 0.05 m thick
Cyclopean concrete footing0.40 m thick, set 0.30 m in from the lean-concrete edge
Masonry wall≈3.40 m high, 0.70 m top width, battered face on the LEFT
Working space (end condition)0.50 m (0.45 m is the “normal” minimum for a worker)
Lecturer repeated these most ① Name + style each component BEFORE adjusting points (“as dogma”, about 6 times) — points take the component’s style when created, and outputs are filtered by style; it saves 15–20 minutes.
② Constrain every point to the base; keep the alignment-held points green (free). “When it goes down, everything goes down” — like the critical path in a schedule.
③ Press Apply, or nothing happens.

Point colours

  • Green = no constraint (free)
  • Yellow = one constraint
  • Red = both (horizontal + vertical)

Component vs end condition

  • Component: closed shape, known size, quantity predictable (wall, concrete, pavement).
  • End condition: open, seeks the surface, models the unknown part — earthwork. Cut goes up, fill goes down.
Why “Infinite”? The wall is fully buried, so the OGL may be 5, 10 or 30 m above. A fixed 5 m segment would fail wherever the ground is higher. Why interception OFF on the first 0.5 m? So it doesn’t stop on ground right next to the wall. The second segment must search, because nobody knows where the OGL will be hit. (Got “End Condition Conflicts”? Check the end-condition priority.)
19

Roadway Designer: corridor → cross-sections → quantities

Session 3 · voice recording

Corridor = horizontal + vertical + template. Active surface = OGL. Drop the template every 5 m, tie the bottom point to VL Bottom, create the design surface, then cut cross-sections.

  1. Modeler → Roadway Designer — it combines the three separate pieces: horizontal, vertical, typical section.
  2. Corridor → Corridor Management — name the corridor, horizontal = your alignment, vertical = VL Top (because the origin is at the top) → Add → Close.
  3. Active Surface = OGL — not the as-built. The as-built only gives the wall top; volumes are measured from the OGL.
  4. Corridor → Template Drops — interval 5 m (the wall is about 50 m long; 10, 20 or 25 m are other options), pick the template → Add. If an end condition doesn’t appear, it found no OGL on that side.
  5. Corridor → Point Controls — point = the bottom (lean-concrete) point, mode = Vertical, controlled by vertical alignment VL Bottom → Add. The lecturer: “the main purpose we came for”.
  6. Template drop shows red? → Synchronize with Library.
  7. Corridor → Create Surface — name “design”, tick Empty Design Surface and Triangulate → Apply. Save the roadway (.ird) and template library (.itl) separately.
  8. Evaluation → Cross Section → Create Cross Section — set each surface’s style (design → “use features”, OGL → Existing Ground, As-built, Rock top, RL), interval 5 m, and left/right offsets wide enough (too small and the section is clipped).

Why do it in software?

By hand you cut a section every 20 m and use the end-area method; measuring masonry in CAD is slow. A well-built template gives automatic sections at any interval and quantities by component name (masonry, cyclopean, lean concrete, excavation).

Real cut slopes vs the model

Soil can’t stand vertical (angle of repose), and trenches deeper than about 1 m can collapse on workers. Real road cuts are sloped — flatter for shallow cuts, steeper for deep ones, about 1:1 in rock. For this quantity calculation a vertical cut was used.

Corridors: one corridor = one site or segment with its own alignment and template. A project can have 30–40 of them. Make cross-sections per corridor, not all together, or they get mixed up.
?

Practice quiz

Instant feedback · explanations link back to the notes

Answer, read the explanation, move on. Use Retry wrong ones at the end to drill your mistakes.

Aa

Glossary

Terms as used in class
AADT
Annual Average Daily Traffic — average vehicles per day; decides the design class.
Design class (DC1–DC8)
ERA traffic-based road class; DC8 is the highest (10,000–15,000 AADT).
Carriageway
The part of the road vehicles drive on.
Shoulder
Strip beside the carriageway; pedestrians, stopped vehicles, edge protection.
Median
Strip separating opposite directions; wide outside towns for future lanes.
Back slope / side slope
Cut slope going up to ground / fill slope going down to ground.
Berm / bench
Flat step on a high slope; breaks the slope, diverts water.
OMC
Optimum Moisture Content — water content giving maximum compacted density.
Expansive soil
Clay that swells when wet and shrinks when dry; causes potholes.
SSD / PSD
Stopping / Passing Sight Distance.
Crest / sag curve
Vertical curve over a hill top / through a valley.
Superelevation
Banking of the road on a curve; max 8% rural, 4% urban.
Run-off length (L)
Length over which the outer edge goes from −2.5% to full superelevation.
Transition (spiral) curve
Gradual curve between tangent and circular curve.
Curve widening
Extra width on tight curves (none if R > 250 m).
PI / PC / PT
Point of Intersection of tangents / start of curve / end of curve.
PVI
Point of Vertical Intersection (vertical alignment).
Station (chainage)
Distance along the alignment, e.g. 0+120.
Benchmark (BM)
Surveyed reference point of known elevation.
OGL / OG
Original Ground Level — natural surface before works.
As-built
Survey of what was actually constructed.
RL
Reduced Level — here the bottom / founding level surface.
TIN / triangulate
Surface made by joining survey points into triangles.
Seed name
Name given to an imported batch of points so it can be filtered or deleted later.
Symbology
Colour / line style of a surface or element in plan, profile, section.
Template
Typical cross-section applied along an alignment.
Component
Closed shape in a template with known size (wall, concrete, pavement).
End condition
Open template part that seeks a target surface (earthwork).
Check for interception
Lets an end-condition segment stop where it meets the surface.
Template origin
Point that rides the horizontal + vertical alignment.
Corridor
3D model = alignment + template (+ controls) for one site or segment.
Template drop
Placing the template along the corridor at an interval (5 m in class).
Point control
Forces a template point to follow another alignment (bottom → VL Bottom).
Active surface
The surface end conditions target — OGL.
End-area method
Volume = (A₁ + A₂) / 2 × distance between sections.
CBR
California Bearing Ratio — strength test of soil.
Atterberg limits / PI
Moisture limits of clay behaviour / Plasticity Index.
Capping material
Better-quality layer placed over weak subgrade.
Weep hole
Drain hole through a retaining wall that releases water pressure.
Surcharge load
Extra load on top of soil (e.g. traffic) that pushes on slopes and walls.
Lean / cyclopean concrete
Thin blinding layer / concrete with large stones (wall footing).